Why sign-off decides whether you get paid for extras
Disputes about extra work are often not about whether the work was done. They are about whether anyone agreed to it and how much of it there was. A ticket that was filled in on site and signed by the right person answers both questions before they are asked. A ticket that was written up from memory a week later usually does not.
On site: what to record
- Date and job: job name, PO or contract number, location or area of the site.
- What was asked and by whom: the person who requested the extra work, and what they said.
- Crew: names or roles and hours for each person.
- Equipment: what was used and for how long.
- Materials: what was used, with quantities.
- Description of the work in a sentence or two, in plain words.
- Photos: before, during or after, with the time stamp.
- Signature: name, title and time of the person signing for the customer.
A sample ticket
Invented sample for illustration.
T&M ticket #T-0412 · [Job name / PO] · [Date]
Requested by: [name, title] at [time] – "extend the supply line past the east wall"
Crew: 2 people × 3 hours
Equipment: scissor lift, 3 hours
Materials: 12 m of 2-inch pipe, 4 fittings
Description: Extended supply line as requested; not in the original scope.
Photos: 2 attached
Signed: [name, title] at [time]
After the work: the same-day routine
- Send the ticket for signature before the crew leaves the site, or that afternoon.
- If it is still unsigned the next morning, send one short, polite reminder.
- Put the signed ticket with the job file and match it to a line on the next invoice.
- Flag any ticket unsigned after two or three days to the person who handles the customer, instead of letting it age.
- At month end, compare signed tickets to invoice lines. Anything signed but not billed is money left on the table.
Change orders: agree before the work if you can
For anything bigger than a few hours, a change order signed before the work protects you better than a ticket signed after. State what is changing, the price or rate, any schedule impact and who is authorised to approve it. If a verbal go-ahead is all you can get, write it down and send it back for confirmation the same day.
Where this connects to getting paid
The invoice should reflect the tickets. Alberta's prompt payment rules also require a proper invoice to show the period of work and a description of it, and signed tickets give you the dates and descriptions to build those from. The payment clock starts when the owner receives a proper invoice, so the sooner tickets turn into invoices, the sooner it starts.
Get-Paid runs this routine for you (built and tested on sample data): the crew fills a short phone form, the super signs by text link, unsigned tickets get reminders and you see what is stuck. The Paperwork Desk demo shows sample field tickets being checked before anyone types them.
Questions people ask
What is the difference between a T&M ticket and a change order?
A T&M (time-and-materials) ticket records hours, crew and materials for work done, often when the scope is open. A change order records an agreed change to scope or price, ideally before the work starts. Many jobs need both.
Who should sign a field ticket?
Someone with authority on the customer side, usually the site superintendent or project manager. Record their name, title and the time they signed.
What if the super will not sign?
Do not argue on site. Record the work with photos, note who asked for it, tell the customer in writing the same day, and raise it with your own office. Ask a lawyer about your contract rights.
How soon should a ticket be signed?
As close to the work as you can manage, ideally the same day, when everyone remembers it.
Can tickets be signed on a phone?
Often, yes. A text or email link to a short form with a finger signature is a common approach. Check that your contract accepts electronic sign-off, and keep the photos and the time stamp.
How does this connect to Alberta's prompt payment rules?
A proper invoice needs the period of work and a description of it. Signed tickets give you the dates and descriptions to build those from. See our proper invoice checklist. This is not legal advice.
Sources
- BLG, Overview of Alberta's Prompt Payment and Construction Lien Act
- Miller Thomson, Alberta's new prompt payment and construction lien legislation: an overview
This page is general information, not legal advice. Check your contract, and talk to a construction lawyer about disputes.