The Alberta Prompt Payment clock on one page, with a calculator

Alberta's Prompt Payment and Construction Lien Act sets deadlines for paying invoices on construction work. Here is the timeline in plain language, a free calculator for your own dates, and an example so you can see which day is which.

By Paras, Evenstead Automation, Edmonton · Last updated

What this page is for

If you do construction work in Alberta, the Prompt Payment and Construction Lien Act (PPCLA) puts dates on when an invoice must be paid and when payment must flow down to the people below you. The dates are easy to miss, and they start with one thing: a proper invoice.

This page puts the timeline in one place, with a calculator for your own dates. It is based on two public law-firm overviews, linked at the bottom. If a number matters to a real dispute, read the Act itself.

The clock at a glance

StepWhoDeadline (as summarised)
Send a proper invoiceContractor to ownerAt least every 31 days. BLG notes an exception where the contract provides for testing and commissioning; Miller Thomson describes that exception differently, so check the Act.
Notice of disputeOwnerWithin 14 days of receiving the invoice, if disputing any part
Pay the invoiceOwner to contractorWithin 28 days of receiving a proper invoice; undisputed amounts are still due in 28 days
Pass payment downContractor to subcontractorWithin 7 days of being paid, for the work the owner paid for, unless a notice of non-payment is given
Outside date if the owner has not paidContractor to subcontractor35 days from giving the proper invoice to the owner, if no notice of non-payment is given
Outside date further downSubcontractor to sub-subcontractor42 days from the proper invoice being given to the owner, if no notice of non-payment is given
Notice of non-paymentContractor to subcontractorWithin 7 days of receiving the owner's notice of dispute or, if none, within 35 days of giving the proper invoice to the owner, per BLG
Start adjudication against the ownerContractor, after a non-payment notice based on the owner's non-paymentWithin 21 days of giving that notice, per BLG

Deadline calculator

Pick the date the owner received your proper invoice (and, if different, the date you gave it). The page counts calendar days forward and shows the dates law-firm summaries give. Nothing you enter is sent anywhere; it stays in your browser.




StepRule as summarisedDate
Owner's notice of disputeWithin 14 days of receiving the invoiceEnter a date
Owner's payment dueWithin 28 days of receiving a proper invoiceEnter a date
Contractor must pay subcontractor by (outside date)35 days from giving the proper invoice to the owner, if no notice of non-paymentEnter a date
Subcontractor must pay sub-subcontractor by (outside date)42 days from the proper invoice being given to the owner, if no notice of non-paymentEnter a date
Pass payment downWithin 7 days of being paid, for the work the owner paid for, unless a notice of non-payment is givenEnter the paid date

How to use it

  1. Use the date the owner actually received the invoice, with proof (email time stamp, portal receipt, signed ticket).
  2. Check the invoice was a proper invoice. The clocks start from a proper invoice; our proper invoice checklist lists what that means.
  3. Put the dispute date and the payment-due date in your calendar as soon as you have proof the invoice was received.
  4. If the owner pays, enter the paid date to see when your own payment to a subcontractor is due.

The dates are calendar days from the date entered. Check the Act for how days are counted in your situation.

A worked example: one invoice, day by day

Example with made-up numbers.

  1. Day 0: a mechanical contractor delivers a proper invoice to the owner.
  2. Day 14: the last day for the owner to give a notice of dispute. None arrives.
  3. Day 28: the owner's payment is due. The owner pays in full on day 25.
  4. Day 32: the contractor has 7 days from being paid (until day 32) to pay its electrical subcontractor.
  5. Alternative path: if the owner had not paid, the contractor's outside date to pay the subcontractor, unless it gave a notice of non-payment, would be day 35.

The first clock starts only when a proper invoice is delivered. An invoice missing required details can leave you arguing about whether the clock started.

What this clock does not cover

  • Liens and holdback have their own rules and deadlines. Both sources report a general lien registration period of 60 days (up from 45), with 90 days for oil and gas wells and well sites and for concrete work other than ready-mix. When the period starts depends on the type of work. See Alberta lien deadlines and the paper trail, and confirm in the Act or with a lawyer.
  • Exclusions. BLG's overview lists public works under the Public Works Act, certain agreements with the provincial Crown, and projects on lands administered by the federal government.
  • Your contract. A contract can add requirements, such as extra items on an invoice.

How to keep your own clock

  1. Write the invoice delivery date on the invoice itself and in your calendar.
  2. Set reminders for day 14 (dispute window closes), day 28 (payment due) and day 35 (outside date for subcontractors).
  3. Keep proof of delivery: the email, the portal receipt or the signed ticket attached to it.
  4. If something is disputed, write down the date you received the notice. Many later deadlines are measured from it.

Keeping these dates, sending the invoice with proof of delivery and reminding people before each date is the part that slips. That dated record is what Get-Paid (built and tested on sample data) is designed to keep. It will not decide whether your invoice meets the Act.

Questions

When did Alberta's prompt payment rules start?

The Prompt Payment and Construction Lien Act came into force on August 29, 2022. It applies to contracts entered into on or after that date. BLG reports that older contracts still running had to be brought in line by August 29, 2024.

How long does an owner have to pay a contractor?

Law-firm summaries say 28 days from receiving a proper invoice. If the owner disputes the invoice, a notice of dispute is due within 14 days of receiving it, and any undisputed part is still due within the 28 days.

How long does a contractor have to pay a subcontractor?

Generally 7 days after the contractor is paid, with outside dates if the owner has not paid and no notice of non-payment is given: 35 days from the proper invoice for a subcontractor, and 42 days down the chain for a sub-subcontractor, per BLG's overview.

Does the 28-day clock start when I send the invoice?

The summaries say it runs from the owner receiving a proper invoice. Keep proof of the date it was received.

What does the calculator show, and does my data leave my browser?

From the date an owner received a proper invoice, it shows the dates law-firm summaries give: 14 days for a notice of dispute, 28 days to pay, and the 35 and 42-day outside dates for subcontractors. Enter a paid date to see 7 days to pass payment down. The dates are worked out in your browser and nothing is sent or stored.

What counts as a proper invoice?

The Act sets out required contents. See our proper invoice checklist for a plain-language list, and check the Act for the exact requirements.

What is adjudication?

A faster, out-of-court way to resolve payment disputes. An adjudicator is appointed through a nominating authority. Time limits and rules apply, so read the Act or ask a lawyer before starting one.

Does this cover liens and holdback?

This page does not. Lien and holdback rules are separate and have their own deadlines. Both sources report a general lien registration period of 60 days (up from 45), with 90 days for oil and gas wells and well sites and for concrete work other than ready-mix. When the period starts depends on the type of work. Confirm all lien deadlines in the Act or with a lawyer.

Are all projects covered?

No. BLG's overview lists exclusions such as public works under the Public Works Act, certain agreements with the provincial Crown, and projects on lands administered by the federal government. Your contract may also add requirements.

Sources

This is general information, not legal advice: a plain-language summary of two public law-firm overviews, last checked October 12, 2026.