Under Alberta's Prompt Payment and Construction Lien Act, the payment clock starts when the owner receives a proper invoice. Here is what law-firm summaries say it must contain, as a checklist you can copy.

By Paras, Evenstead Automation, Edmonton · Last updated

Why the invoice matters

In Alberta, the owner's 28 days to pay start when a proper invoice is received. If an invoice is missing something the Act requires, the owner may argue it is not a proper invoice, and you can lose weeks arguing about the paperwork instead of being paid. This page is a checklist for avoiding that. See the full payment clock for what happens after.

The checklist

Based on two law-firm summaries (linked below), a proper invoice is a written bill or payment request for work done or materials furnished that shows:

  1. Your name and business address (the contractor's or subcontractor's).
  2. The invoice date and the period the work was done or the materials were furnished.
  3. The authority for the work: the contract, written or verbal, or other basis.
  4. A description of the work or materials.
  5. The amount requested and the payment terms, broken down by work or materials.
  6. The name, title and contact details of the person to be paid.
  7. A statement that the invoice is intended to be a proper invoice.
  8. Anything else the regulations or your contract require.

Timing: both summaries say a proper invoice goes to the owner at least every 31 days. BLG notes a testing and commissioning exception that Miller Thomson describes differently; check the Act.

A sample layout

Invented sample for illustration. Adjust it to your business and contract.

[Your company name], [business address]
Invoice #: 2026-014 · Invoice date: [date]
Work period: [start date] to [end date]
Authority for work: [Written contract dated ___ / change order #__ / verbal agreement on ___]
Description: [Labour: 24 hours; Materials: item list]
Amount requested: $[labour] + $[materials] = $[total]
Payment terms: [as per contract]
Pay to: [name, title, phone, email]
This invoice is intended to be a proper invoice under the Prompt Payment and Construction Lien Act.

Common mistakes

  • Leaving off the work period. The invoice date alone is not enough.
  • Lumping labour and materials into one number instead of breaking it down.
  • No named person to pay, so it goes to a general mailbox.
  • No statement that it is a proper invoice.
  • Letting more than 31 days pass between invoices.
  • No proof of delivery. Keep the email or portal receipt.

Where signed tickets fit

An invoice is easiest to write and defend when the extra work already has a signed ticket behind it. See our field ticket sign-off checklist. Get-Paid (built and tested on sample data) is designed to turn a signed ticket into a draft invoice line for your approval. You still decide whether the invoice meets the Act.

Questions people ask

What is a proper invoice in Alberta?

Under the Prompt Payment and Construction Lien Act, a written bill or payment request for work done or materials furnished that contains the information the Act and your contract require. The 28-day payment clock for the owner starts when a proper invoice is received.

Does it have to say it is a proper invoice?

Law-firm summaries list a statement that the invoice is intended to be a proper invoice among the required contents.

How often must I invoice?

Both summaries say at least every 31 days. BLG notes an exception where the contract provides for testing and commissioning; check the Act for how it applies.

What if my contract asks for more on the invoice?

A contract can add requirements. Follow both the Act and your contract.

Can I use my accounting software's invoice?

Often yes, if it can show all the required items. Add the missing ones, such as the period of work and the proper invoice statement, as a template or note.

Is this legal advice?

No. It is a plain-language summary of public sources. Check the Act or a construction lawyer.

Sources

Automating the paper trail: invoice and document automation.

Not legal advice. This page is a plain-language summary of two public law-firm overviews, last checked October 12, 2026. The law and your contract may differ, and some projects are excluded. Check the Act itself or talk to a construction lawyer.